What changed and what matters
Source-linked public evidence, with historical, target and current-review semantics kept distinct.
Production Increase Plan Committee Continues Field Tours and Visits to Waha and Harouge Oil Fields
Ghani field
NOC’s Production Increase Plan Committee inspected Harouge’s Ghani field, including production facilities and critical infrastructure, and discussed technical, administrative and financial challenges affecting operations and priority projects.
Open source evidence →Engineer Masoud Suleman Congratulates Harouge Team on Successful Commissioning of Well B79A
Amal exploration area
Harouge drilled, connected and commissioned replacement well B79A under its approved 2026 plan; NOC reported technical flow tests at nearly 2,000 barrels of oil per day with water content below 4%.
Open source evidence →Harouge Fast-Tracks Maintenance on Tank 10 and Clears Messla-Sarir Pipeline for Action
Ras Lanuf Port / Messla-Sarir crude system
Harouge reviewed accelerated maintenance and preparation of Tank 10 and work to prepare the 30-inch Messla-Sarir crude pipeline and pumping system for receipt and pumping of crude to the Ras Lanuf Refinery.
Open source evidence →Constraints and operating attention
NOC’s Production Increase Plan Committee inspected Harouge’s Ghani field, including production facilities and critical infrastructure, and discussed technical, administrative and financial challenges affecting operations and priority projects.
Harouge reviewed accelerated maintenance and preparation of Tank 10 and work to prepare the 30-inch Messla-Sarir crude pipeline and pumping system for receipt and pumping of crude to the Ras Lanuf Refinery.
Projects, targets and development
NOC’s Production Increase Plan Committee inspected Harouge’s Ghani field, including production facilities and critical infrastructure, and discussed technical, administrative and financial challenges affecting operations and priority projects.
Harouge drilled, connected and commissioned replacement well B79A under its approved 2026 plan; NOC reported technical flow tests at nearly 2,000 barrels of oil per day with water content below 4%.
Harouge reviewed accelerated maintenance and preparation of Tank 10 and work to prepare the 30-inch Messla-Sarir crude pipeline and pumping system for receipt and pumping of crude to the Ras Lanuf Refinery.
View all 3 verified evidence records
| Scope | Date | Topic | Metric / signal | Status | Source |
|---|---|---|---|---|---|
| HAROUGE | 26 Sep 2026 | Production / Projects / Reliability / Oversight | Production-increase project constraints at Ghani | 2026 signal | Evidence |
| HAROUGE | 05 Sep 2026 | Production / Well Development | B79A test oil production | Historical point in time | Evidence |
| HAROUGE | 17 May 2026 | Maintenance / Export Infrastructure / Reliability | Tank 10 and Messla-Sarir export-system maintenance | Historical point in time | Evidence |