LibyaSense Intelligence
Verified public-source intelligence across the covered Libyan energy portfolio, organized for executive scanning, traceability and decision support.
What changed and what matters
Source-linked public evidence, with historical, target and current-review semantics kept distinct.
Hamada–Zawiya Crude Oil Pipeline Valve Shut Down
Hamada and Tahara fields / Zawiya crude reception
NOC reported that unauthorized individuals closed an isolation valve on the 18-inch crude oil pipeline carrying AGOCO crude from the Hamada and Tahara fields to the Zawiya reception area; NOC warned that continued blockage would force production halts, damage operational stability and reduce national oil revenues.
Open source evidence →NOC and Brega discuss infrastructure development and fuel-supply system
Brega depots / loading and unloading facilities / supply lines from Zawiya refinery
NOC and Brega reviewed current projects and fuel-supply infrastructure; the meeting called for increased storage capacity and depot/loading-unloading readiness, addressing transport and pumping-line bottlenecks, resolving stalled-project obstacles, and preparing supply-line engineering studies from Zawiya refinery for targeted quantity increases.
Open source evidence →NOC Meets with Zallaf to Discuss Ongoing Exploration Strategy
NOC and Zallaf reviewed 2026 exploration activity and progress against plans, and discussed proposed 2027 exploration programs, budget, and required technical and financial resources.
Open source evidence →NOC Releases Comprehensive Schedule of Daily Revenues Collected Between October 1 and October 14, 2026
Libya (national)
NOC reported USD 1,447,655,717.37 collected between 1 and 14 October 2026 and remitted directly to the sovereign account held at the Libyan Foreign Bank.
Open source evidence →Clarifying Statement on Oil Revenues and the Associated Remittance Mechanism
Libya (national)
NOC stated that cumulative funds remitted to the designated sovereign account stood at USD 1,231,631,354.16 as of 13 October 2026 and described the associated settlement mechanism.
NOC stated that government-approved budget allocations had not been disbursed and said this constrained financial commitments, production stability, development initiatives and maintenance programs.
Open source evidence →NOC and GECOL Discuss Boosting Power Supply Stability to Oil Fields
Libya oil fields / discovered undeveloped fields
NOC and GECOL discussed accelerating electrical interconnections for discovered but undeveloped oil fields and recurring power outages at fields affected by grid instability; NOC stated these outages have made it harder to meet daily and monthly production targets, and the parties agreed to continue coordination and track implementation/results.
Open source evidence →NOC Concludes First Technical Meetings for Petroleum Training and Qualifying Institutes
Petroleum Training and Qualifying Institute, Ajdabiya
NOC concluded the first technical meetings for its Petroleum Training and Qualifying Institute in Ajdabiya, reviewing operations, training and qualification plans, implementation progress, needs and challenges, completed and stalled projects, finances, and facility readiness.
Open source evidence →NOC Lays Foundation Stone for New Tajoura Oil Depot to Modernize Infrastructure and Increase Storage Capacity
Tajoura Oil Depot
NOC reported the foundation stone for the Tajoura Oil Depot, part of Brega's 2025-2029 development plan, in partnership with OLA Energy under a Build-Operate-Transfer model.
Open source evidence →Constraints and operating attention
NOC reported that unauthorized individuals closed an isolation valve on the 18-inch crude oil pipeline carrying AGOCO crude from the Hamada and Tahara fields to the Zawiya reception area; NOC warned that continued blockage would force production halts, damage operational stability and reduce national oil revenues.
NOC and Brega reviewed current projects and fuel-supply infrastructure; the meeting called for increased storage capacity and depot/loading-unloading readiness, addressing transport and pumping-line bottlenecks, resolving stalled-project obstacles, and preparing supply-line engineering studies from Zawiya refinery for targeted quantity increases.
NOC stated that government-approved budget allocations had not been disbursed and said this constrained financial commitments, production stability, development initiatives and maintenance programs.
NOC and GECOL discussed accelerating electrical interconnections for discovered but undeveloped oil fields and recurring power outages at fields affected by grid instability; NOC stated these outages have made it harder to meet daily and monthly production targets, and the parties agreed to continue coordination and track implementation/results.
NOC reported review of Sirte Oil Company projects including final preparations to bring a gasoline production unit online during the week of 12 October 2026, a 30 MW fourth power plant at the petrochemical complex, and plans to restart the gas processing unit.
Projects, targets and development
NOC and Brega reviewed current projects and fuel-supply infrastructure; the meeting called for increased storage capacity and depot/loading-unloading readiness, addressing transport and pumping-line bottlenecks, resolving stalled-project obstacles, and preparing supply-line engineering studies from Zawiya refinery for targeted quantity increases.
NOC and Zallaf reviewed 2026 exploration activity and progress against plans, and discussed proposed 2027 exploration programs, budget, and required technical and financial resources.
NOC stated that government-approved budget allocations had not been disbursed and said this constrained financial commitments, production stability, development initiatives and maintenance programs.
NOC concluded the first technical meetings for its Petroleum Training and Qualifying Institute in Ajdabiya, reviewing operations, training and qualification plans, implementation progress, needs and challenges, completed and stalled projects, finances, and facility readiness.
NOC reported the foundation stone for the Tajoura Oil Depot, part of Brega's 2025-2029 development plan, in partnership with OLA Energy under a Build-Operate-Transfer model.
View all 70 verified evidence records
| Scope | Date | Topic | Metric / signal | Status | Source |
|---|---|---|---|---|---|
| NOC | 22 Oct 2026 | Production / Infrastructure / Operational Risk | Hamada–Zawiya pipeline valve closure threatening production continuity | 2026 signal | Evidence |
| BREGA | 19 Oct 2026 | Fuel Supply / Storage / Infrastructure / Projects / HSE | Fuel-supply infrastructure bottlenecks and stalled-project constraints | 2026 signal | Evidence |
| NOC | 15 Oct 2026 | Exploration / Strategy / Portfolio | Zallaf 2027 exploration program and budget planning | 2026 signal | Evidence |
| NOC | 15 Oct 2026 | Financial / Revenue / Transparency | Oil revenues remitted to sovereign account | Historical point in time | Evidence |
| NOC | 15 Oct 2026 | Financial / Revenue / Governance / Transparency | Cumulative funds remitted to designated sovereign account | Historical point in time | Evidence |
| NOC | 15 Oct 2026 | Financial / Operational Risk / Maintenance / Development | Withheld budget allocations constraining operational plans | 2026 signal | Evidence |
| NOC | 14 Oct 2026 | Production / Reliability / Infrastructure / Power Supply | Power-supply reliability constraint affecting oil-field production targets | 2026 signal | Evidence |
| NOC | 14 Oct 2026 | Capability Development / Training Governance | Petroleum training institute governance / capability-development review | 2026 signal | Evidence |
| NOC | 14 Oct 2026 | Infrastructure / Storage / Fuel Supply / Commercial Model | Tajoura Oil Depot development | 2026 signal | Evidence |
| NWD | 13 Oct 2026 | Rig / Fleet / Integrity / Procurement | Rig 15 DS-1 CAT 4 inspection procurement signal | Historical / closed window | Evidence |
| NWD | 13 Oct 2026 | ICT / Connectivity / Procurement | Satellite internet services for NWD-owned rigs | Historical / closed window | Evidence |
| AGOCO | 13 Oct 2026 | Water Management / Procurement / Environment | Produced-water disposal and injection project prequalification | 2026 signal | Evidence |
| NOC | 12 Oct 2026 | Downstream / Projects / Operations / HSE / Gas Flaring | Sirte petrochemical-complex fourth power plant capacity | 2026 signal | Evidence |
| NOC | 08 Oct 2026 | Gas / Project / Production / Infrastructure Readiness | Bouri gas volume for planned receipt/processing/use | 2026 signal | Evidence |
| NWD | 07 Oct 2026 | Rig / Fleet / Integrity / Procurement | DP-3 Offshore Rig major-overhaul integrity activity | Historical / closed window | Evidence |
| NWD | 28 Sep 2026 | Procurement / Inspection | Rig 25 / Rig 24 inspection services | Historical / closed window | Evidence |
| NWD | 28 Sep 2026 | Procurement / Inspection | Rig 25 / Rig 24 RFQ closing date | Historical / closed window | Evidence |
| WAHA | 26 Sep 2026 | Production / Projects / Oversight | Production-increase plan field oversight | 2026 signal | Evidence |
| HAROUGE | 26 Sep 2026 | Production / Projects / Reliability / Oversight | Production-increase project constraints at Ghani | 2026 signal | Evidence |
| AGOCO | 25 Sep 2026 | Production / Projects / Reliability / Oversight | Production-increase project obstacles | 2026 signal | Evidence |
| NWD | 22 Sep 2026 | Offshore Drilling / Procurement | Subsea BOP minimum working pressure | Historical / closed window | Evidence |
| NWD | 22 Sep 2026 | Offshore Drilling / Procurement | Offshore semi-submersible prequalification deadline | Historical / closed window | Evidence |
| HAROUGE | 05 Sep 2026 | Production / Well Development | B79A test oil production | Historical point in time | Evidence |
| NOC | 26 Aug 2026 | Strategy / Targets | Crude oil production target | Active target | Evidence |
| WAHA | 25 Aug 2026 | Export / Measurement / Infrastructure | Sidra export fiscal metering system | 2026 signal | Evidence |
| NWD | 17 Aug 2026 | Drilling & Workover Performance | Wells maintained | 2026 review | Evidence |
| NWD | 17 Aug 2026 | Drilling & Workover Performance | Wells drilled | 2026 review | Evidence |
| NWD | 17 Aug 2026 | Capability Development | Drilling engineering department | 2026 review | Evidence |
| NWD | 17 Aug 2026 | Capability Development | Integrated drilling projects | 2026 review | Evidence |
| NWD | 17 Aug 2026 | Operational Risk / Reliability | Overdue client payments affecting fleet readiness | 2026 review | Evidence |
| WAHA | 12 Aug 2026 | Production | Waha oil production | 2026 review | Evidence |
| WAHA | 12 Aug 2026 | Strategy / Targets | 2026 incremental production target | Active target | Evidence |
| WAHA | 12 Aug 2026 | Production Performance | Incremental production achieved against 2026 plan | Historical point in time | Evidence |
| WAHA | 12 Aug 2026 | Drilling / Development | 2026 drilling program wells | 2026 review | Evidence |
| WAHA | 12 Aug 2026 | Operational Risk / Reliability | Pipeline leaks and funding constraints | 2026 signal | Evidence |
| NWD | 20 Jul 2026 | Procurement / Inspection | Rig 8 inspection scope | Historical / closed window | Evidence |
| NOC | 16 Jul 2026 | Exploration / Development | Estimated oil reserves | 2026 signal | Evidence |
| NOC | 16 Jul 2026 | Exploration / Development | Expected production capacity | 2026 signal | Evidence |
| NOC | 16 Jul 2026 | Exploration / Development | Commercial viability / development operator | 2026 signal | Evidence |
| SIRTE | 04 Jul 2026 | Production / Well Rehabilitation / Artificial Lift | J-03 initial post-ESP production rate | Historical point in time | Evidence |
| MELLITAH | 29 Jun 2026 | Gas / Compression / Reliability / Production | Expected annual gas-production increase | 2026 signal | Evidence |
| NOC | 21 Jun 2026 | Production | Crude oil production | Historical point in time | Evidence |
| NOC | 21 Jun 2026 | Production | Condensate production | Historical point in time | Evidence |
| NOC | 21 Jun 2026 | Production | Total daily output | Historical point in time | Evidence |
| NOC | 21 Jun 2026 | Production | Production milestone | Historical point in time | Evidence |
| NOC | 21 Jun 2026 | Strategy / Targets | Crude oil production target | Active target | Evidence |
| AGOCO | 11 Jun 2026 | Production / Well Optimization | B1-NC2 oil production after intervention | Historical point in time | Evidence |
| HAROUGE | 17 May 2026 | Maintenance / Export Infrastructure / Reliability | Tank 10 and Messla-Sarir export-system maintenance | Historical point in time | Evidence |
| SIRTE | 12 May 2026 | Petrochemicals / Reliability / Utilities | Methanol I and Nitrogen II restart | Historical point in time | Evidence |
| LIFECO | 25 Apr 2026 | Production / Urea | Urea production | Historical point in time | Evidence |
| LIFECO | 25 Apr 2026 | Exports / Urea | Urea exports | Historical point in time | Evidence |
| LIFECO | 25 Apr 2026 | Exports / Ammonia | Ammonia exports | Historical point in time | Evidence |
| LIFECO | 25 Apr 2026 | Production Performance / Urea II | Urea II March target attainment | Historical point in time | Evidence |
| NWD | 21 Apr 2026 | Procurement / Inspection | Rig 21 CAT IV NDT inspection | Historical / closed window | Evidence |
| NWD | 21 Apr 2026 | Procurement / Inspection | Rig 21 RFQ closing date | Historical / closed window | Evidence |
| MELLITAH | 10 Apr 2026 | Production / Well Rehabilitation / Artificial Lift | R11 post-rehabilitation production rate | Historical point in time | Evidence |
| NOC | 16 Mar 2026 | Exploration / Development | Estimated gas reserves | 2026 signal | Evidence |
| NOC | 16 Mar 2026 | Exploration / Development | Expected gas contribution | 2026 signal | Evidence |
| NOC | 16 Mar 2026 | Exploration / Development | Tie-in distance to Bahr Essalam platform | 2026 signal | Evidence |
| AGOCO | 06 Mar 2026 | Production / Well Development | Z-13 initial oil production | Historical point in time | Evidence |
| SIRTE | 28 Feb 2026 | Production / Development Drilling / Reservoir | T27-13 initial oil production rate | Historical point in time | Evidence |
| AGOCO | 04 Feb 2026 | Production / Well Development | L-028HR oil production | Historical point in time | Evidence |
| AGOCO | 04 Feb 2026 | Refining / Reliability / Maintenance | Sarir refinery crude distillation unit overhaul and restart | Historical point in time | Evidence |
| ZALLAF | 13 Nov 2025 | Production / Export / Field Development | Shadar first oil and condensate shipment | Historical point in time | Evidence |
| LIFECO | 08 Oct 2025 | Governance / Operational Performance | Ammonia and urea operational-performance review | Historical point in time | Evidence |
| LIFECO | 21 Sep 2025 | Maintenance / Critical Assets | Urea I SG-1011 B boiler replacement | Historical point in time | Evidence |
| ZALLAF | 10 Aug 2025 | Gas / Field Development / Strategy | Atshan expected gas production | Historical point in time | Evidence |
| ZALLAF | 10 Aug 2025 | Production / Field Development | Shadar oil production | Historical point in time | Evidence |
| LIFECO | 30 Jul 2025 | HSE / Environment / Materials | Safe disposal planning for stagnant chemicals | Historical point in time | Evidence |
| LIFECO | 21 Jan 2025 | Maintenance / Reliability / Ammonia I | Ammonia I primary-reformer catalyst replacement | Historical point in time | Evidence |
Public-source intelligence only. Independent analysis; no confidential company data or endorsement is implied. Data boundaries.