Crude production1.44Mbbl/dayOfficial point-in-time figure where available
Total daily output1.49Mbbl/daySource-stated figure where available
End-2026 crude target1.5Mbbl/dayOfficial target, not current production
Verified NOC evidence24Current governed public-evidence set
LATEST VERIFIED SIGNALS

What changed and what matters

Source-linked public evidence, with historical, target and current-review semantics kept distinct.

NOCProduction / Infrastructure / Operational Risk

Hamada–Zawiya Crude Oil Pipeline Valve Shut Down

22 Oct 20262026 signal

Hamada and Tahara fields / Zawiya crude reception

NOC reported that unauthorized individuals closed an isolation valve on the 18-inch crude oil pipeline carrying AGOCO crude from the Hamada and Tahara fields to the Zawiya reception area; NOC warned that continued blockage would force production halts, damage operational stability and reduce national oil revenues.

Open source evidence →
NOCFinancial / Revenue / Governance / Transparency

Clarifying Statement on Oil Revenues and the Associated Remittance Mechanism

15 Oct 2026Historical point in time

Libya (national)

NOC stated that cumulative funds remitted to the designated sovereign account stood at USD 1,231,631,354.16 as of 13 October 2026 and described the associated settlement mechanism.

NOC stated that government-approved budget allocations had not been disbursed and said this constrained financial commitments, production stability, development initiatives and maintenance programs.

Open source evidence →
NOCProduction / Reliability / Infrastructure / Power Supply

NOC and GECOL Discuss Boosting Power Supply Stability to Oil Fields

14 Oct 20262026 signal

Libya oil fields / discovered undeveloped fields

NOC and GECOL discussed accelerating electrical interconnections for discovered but undeveloped oil fields and recurring power outages at fields affected by grid instability; NOC stated these outages have made it harder to meet daily and monthly production targets, and the parties agreed to continue coordination and track implementation/results.

Open source evidence →
NOCCapability Development / Training Governance

NOC Concludes First Technical Meetings for Petroleum Training and Qualifying Institutes

14 Oct 20262026 signal

Petroleum Training and Qualifying Institute, Ajdabiya

NOC concluded the first technical meetings for its Petroleum Training and Qualifying Institute in Ajdabiya, reviewing operations, training and qualification plans, implementation progress, needs and challenges, completed and stalled projects, finances, and facility readiness.

Open source evidence →
ATTENTION

Constraints and operating attention

NOC
Methane emission alert response rate

NOC reported that UNEP and IMEO recognized a 92% response rate to methane-emission alerts, following specialized MARS and OGMP 2.0 training for focal points across NOC and subsidiaries.

NOC
Hamada–Zawiya pipeline valve closure threatening production continuity

NOC reported that unauthorized individuals closed an isolation valve on the 18-inch crude oil pipeline carrying AGOCO crude from the Hamada and Tahara fields to the Zawiya reception area; NOC warned that continued blockage would force production halts, damage operational stability and reduce national oil revenues.

NOC
Withheld budget allocations constraining operational plans

NOC stated that government-approved budget allocations had not been disbursed and said this constrained financial commitments, production stability, development initiatives and maintenance programs.

NOC
Power-supply reliability constraint affecting oil-field production targets

NOC and GECOL discussed accelerating electrical interconnections for discovered but undeveloped oil fields and recurring power outages at fields affected by grid instability; NOC stated these outages have made it harder to meet daily and monthly production targets, and the parties agreed to continue coordination and track implementation/results.

NOC
Sirte petrochemical-complex fourth power plant capacity

NOC reported review of Sirte Oil Company projects including final preparations to bring a gasoline production unit online during the week of 12 October 2026, a 30 MW fourth power plant at the petrochemical complex, and plans to restart the gas processing unit.

MOMENTUM

Projects, targets and development

NOC
Zallaf 2027 exploration program and budget planning

NOC and Zallaf reviewed 2026 exploration activity and progress against plans, and discussed proposed 2027 exploration programs, budget, and required technical and financial resources.

NOC
Withheld budget allocations constraining operational plans

NOC stated that government-approved budget allocations had not been disbursed and said this constrained financial commitments, production stability, development initiatives and maintenance programs.

NOC
Petroleum training institute governance / capability-development review

NOC concluded the first technical meetings for its Petroleum Training and Qualifying Institute in Ajdabiya, reviewing operations, training and qualification plans, implementation progress, needs and challenges, completed and stalled projects, finances, and facility readiness.

NOC
Tajoura Oil Depot development

NOC reported the foundation stone for the Tajoura Oil Depot, part of Brega's 2025-2029 development plan, in partnership with OLA Energy under a Build-Operate-Transfer model.

NOC
Sirte petrochemical-complex fourth power plant capacity

NOC reported review of Sirte Oil Company projects including final preparations to bring a gasoline production unit online during the week of 12 October 2026, a 30 MW fourth power plant at the petrochemical complex, and plans to restart the gas processing unit.

View all 24 verified evidence records
ScopeDateTopicMetric / signalStatusSource
NOC 25 Oct 2026 Gas / Production / Infrastructure Rashad gas field production capacity 2026 signal Evidence
NOC 25 Oct 2026 HSE / Environment / Methane / Capability Methane emission alert response rate 2026 signal Evidence
NOC 22 Oct 2026 Production / Infrastructure / Operational Risk Hamada–Zawiya pipeline valve closure threatening production continuity 2026 signal Evidence
NOC 15 Oct 2026 Exploration / Strategy / Portfolio Zallaf 2027 exploration program and budget planning 2026 signal Evidence
NOC 15 Oct 2026 Financial / Revenue / Transparency Oil revenues remitted to sovereign account Historical point in time Evidence
NOC 15 Oct 2026 Financial / Revenue / Governance / Transparency Cumulative funds remitted to designated sovereign account Historical point in time Evidence
NOC 15 Oct 2026 Financial / Operational Risk / Maintenance / Development Withheld budget allocations constraining operational plans 2026 signal Evidence
NOC 14 Oct 2026 Production / Reliability / Infrastructure / Power Supply Power-supply reliability constraint affecting oil-field production targets 2026 signal Evidence
NOC 14 Oct 2026 Capability Development / Training Governance Petroleum training institute governance / capability-development review 2026 signal Evidence
NOC 14 Oct 2026 Infrastructure / Storage / Fuel Supply / Commercial Model Tajoura Oil Depot development 2026 signal Evidence
NOC 12 Oct 2026 Downstream / Projects / Operations / HSE / Gas Flaring Sirte petrochemical-complex fourth power plant capacity 2026 signal Evidence
NOC 08 Oct 2026 Gas / Project / Production / Infrastructure Readiness Bouri gas volume for planned receipt/processing/use 2026 signal Evidence
NOC 26 Aug 2026 Strategy / Targets Crude oil production target Active target Evidence
NOC 16 Jul 2026 Exploration / Development Estimated oil reserves 2026 signal Evidence
NOC 16 Jul 2026 Exploration / Development Expected production capacity 2026 signal Evidence
NOC 16 Jul 2026 Exploration / Development Commercial viability / development operator 2026 signal Evidence
NOC 21 Jun 2026 Production Crude oil production Historical point in time Evidence
NOC 21 Jun 2026 Production Condensate production Historical point in time Evidence
NOC 21 Jun 2026 Production Total daily output Historical point in time Evidence
NOC 21 Jun 2026 Production Production milestone Historical point in time Evidence
NOC 21 Jun 2026 Strategy / Targets Crude oil production target Active target Evidence
NOC 16 Mar 2026 Exploration / Development Estimated gas reserves 2026 signal Evidence
NOC 16 Mar 2026 Exploration / Development Expected gas contribution 2026 signal Evidence
NOC 16 Mar 2026 Exploration / Development Tie-in distance to Bahr Essalam platform 2026 signal Evidence

Public-source intelligence only. Independent analysis; no confidential company data or endorsement is implied. Data boundaries.