Estimated Losses of About $75 Million from Sharara Pipeline Shutdown; Concerns About a Possible Zawiya Refinery Closure
Sharara field / Sharara-Zawiya pipeline
NOC reported that the forced closure of Valve No. 7 on the Sharara-Zawiya pipeline sharply reduced Sharara production and stated cumulative lost production of 720,362 barrels over four days through 24 September 2026.
Open source evidence →NOC reviews Akakus technical and financial meeting results and targets Sharara production of 355,000 barrels/day
Sharara field
NOC reported that Sharara field production reached a peak of about 335,000 barrels per day during August 2026.
NOC and Akakus discussed plans targeting total Sharara production of about 355,000 barrels per day by mid-2027, alongside 2027 development drilling, safety projects, reservoir development and surface-equipment upgrades.
Open source evidence →Constraints and operating attention
NOC reported that the forced closure of Valve No. 7 on the Sharara-Zawiya pipeline sharply reduced Sharara production and stated cumulative lost production of 720,362 barrels over four days through 24 September 2026.
Projects, targets and development
NOC and Akakus discussed plans targeting total Sharara production of about 355,000 barrels per day by mid-2027, alongside 2027 development drilling, safety projects, reservoir development and surface-equipment upgrades.
View all 3 verified evidence records
| Scope | Date | Topic | Metric / signal | Status | Source |
|---|---|---|---|---|---|
| AKAKUS | 25 Sep 2026 | Production / Infrastructure / Operational Risk | Sharara-Zawiya pipeline shutdown production constraint | Historical point in time | Evidence |
| AKAKUS | 17 Aug 2026 | Production / Operations / Strategy | Sharara peak production reported for August 2026 | Historical point in time | Evidence |
| AKAKUS | 17 Aug 2026 | Strategy / Targets / Field Development | Sharara production target | Active target | Evidence |